Notification
A notifiable project is one where the construction or works phase is planned to:
- Last over 30 days and involve more than 20 workers at any one time OR
- Involve more than 500 worker days
If the project falls into one or both of these categories then the duty holder (client) is responsible for notifying the HSE of the information listed below:
- The address of the site
- Brief description of the project and construction work involved
- Contact details of the client
- Contact details of the principal designer
- Contact details of the principal contractor
- Planned date for the start of work and planned duration
- Time allowed for planning and preparation for the works
- Estimated maximum number of people at work on the site.